Home > News > Content

What Preparations Should Be Made During The Production Of PVC Foam Board?

Apr 18, 2020

We also introduced the production process of PVC foam board before, because now more and more applications for this product, we are also increasing its production, so this requires us to make more Good production guarantees that its quality can also be better used, so first of all we should be prepared in production,

1. Clean and level the head mold and install it. The opening of the die is generally adjusted to 0.5-2.0mm (depending on the thickness), the middle opening is slightly smaller, and the ends are slightly larger;

2, check whether the waterway, electrical circuit, airway, etc. are normal, and adjust well;

3. Turn on the power of the host and set the temperature of each section:

(1) Reference setting parameters: The first to fourth zones of the PVC foam sheet cylinder are: 170 ° C, 165 ° C, 160 ° C, 150 ° C;

2 (2) Converging core: 140 ° C-145 ° C Screw temperature: 70-95 ° C The middle temperature of the machine head is low on both sides and the temperature is high on both sides: 165-190 ° C;

(3) The setting of the head temperature should not be too high and exceed the decomposition temperature of PVC, which will cause the material performance to decline. After the temperature reaches the set value, it is stable for about 30 minutes to 1 hour;

4. Turn on the feeding machine and a control power supply, adopt hungry feeding and corresponding low-speed extrusion, the feeding speed is 5r / min, and the host speed is 5-6r / min;

5 After the material flows out from the die lip, adjust the feeding and the speed of the host to reach the set value at the same time. The feeding speed is 26-27r / min. The speed of the host is 14-15r / min. The current of the host is about 105A.

For the production of PVC foam board, we must make preparations first. In fact, not only in this aspect, we must also make relevant preparations when doing any other work, so that we can work more Smooth progress, so we are prepared to ensure that our production runs smoothly.



Send Inquiry